True/false - The SOS representative must have some technical understanding
True
How long are SoS meetings time-boxed for?
They are not timeboxed
During sprint review meetings, we evaluate results using ______
EVA(earned value analysis)
What must be updated after the sprint review meeting?
Release planning schedule
Risks
Dependencies
What are the 3 items that need to be identified during a retrospect sprint meeting?
-things that the team needs to keep doing
- things that the team needs to start doing
- things that the team needs to stop doing
________ is an exercise conducted to understand the mindset of the attendees of the retrospect sprint.
ESVP
________ is a technique used to conduct the retrospect meeting
Speed boat
_______ are key output of the retrospect sprint
- Retrospect sprint log which contains opinions, discussions and agreed actionable items(documented and estimated)
Where are' lessons learned' documented?
In the Scrum guidance body.